A certificate purchase order may specify the amount of electricity to be stated in each certificate, and different amounts may be specified in relation to different cases or circumstances.
In particular, different amounts may be specified in relation to—
In this section "banding provision" means provision made in a certificate purchase order by virtue of subsection (1).
Before making any banding provision, the Secretary of State must have regard to the following matters—
For the purposes of subsection (4)(a), the costs associated with generating electricity from a renewable source include any costs associated with the production or supply of heat produced in connection with that generation.
For the purposes of subsection (4)(b), an operator's income associated with the generation of electricity from a renewable source includes any income connected with—
After the first order containing banding provision is made by the Secretary of State, no subsequent order containing such provision may be made by the Secretary of State except following a review held by virtue of subsection (8).
A certificate purchase order may authorise the Secretary of State to review the whole or any part of the banding provision at any time when the Secretary of State is satisfied that one or more of the specified conditions is satisfied.